Faridabad Sector 49 Flat Project
Description about the project

The project is located at Sector-49, Faridabad, Haryana in theland of Village Dabua and Nawadakoh.  Necessary land for this project was acquiredfrom Sri Sat Sahib Housing & Infrastructure Development Company.  Initially about 688 Multi-storey Flats of 4Types i.e. 2BHK, 3BHK, 4BHK and 5BHK will be constructed for the members of theSociety and 122 nos. of EWS Flats will also be constructed for economicallyweaker section.

Clearance from Environmental Department, Airport Authority,Forest Department etc. have already been received.

We have got the Building Plan approved from the District TownPlanner(HQ)Haryana, Chandigarh. Accordingly, the construction work of Flats has already started and thework is progressing in a speedy manner. The completion period of the project is 3 years i.e. upto 2016.

Current Status of site POMSCHS Sector 49,Faridabad Haryana as on Date 26/04/2016.

Tower T5 (3 BHK) :-  Structure Complete, Water Tank complete, Brick Work Complete. Balcony & Stair case Railing complete. Plaster work complete, Outer Plaster Completed, Internal water supply & Plumbing completed, Terrace waterproofing completed. Flooring & Wall tile work Completed. Internal Painting (Putty & Primer) 1st Coarse Completed & 2nd Coarse Started. Door Frame work completed & Window Shutter Fixing 95% Complete  

Tower T6  (3 BHK) :-  Structure Complete, Water Tank complete, Brick Work Complete. Balcony & Stair case Railing complete. Plaster work complete, Outer Plaster Completed, Internal water supply & Plumbing completed, Terrace waterproofing completed. Flooring & Wall tile work Completed. Internal Painting (Putty & Primer) 1st Coarse Completed & 2nd Coarse Started. Door Frame work completed & Window Shutter Fixing 95% Complete  

  Tower T3 (3 BHK)  :- Structure Complete, Water Tank complete, Brick Work Complete. Balcony & Stair case Railing complete. Plaster work complete, Outer Plaster Completed, Internal water supply & Plumbing completed, Terrace waterproofing completed. Flooring & Wall tile work Completed. Internal Painting (Putty & Primer) 1st Coarse Completed. Door Frame work completed & Window Shutter Fixing 95% Complete   

Tower T4 (3 BHK)  :-  Structure Complete, Water Tank complete, Brick Work Complete. Balcony & Stair case Railing complete. Plaster work complete, Outer Plaster Completed, Internal water supply & Plumbing completed, Terrace waterproofing completed. Flooring & Wall tile work Completed. Internal Painting (Putty & Primer) 1st Coarse Completed. Door Frame work completed & Window Shutter Fixing 95% Complete  

Tower T9 (3 BHK) Slab up 5th Floor Casted 100% & Columns for 6th floor is 50% completed. Brick work at 1st & 2nd floor is complete, 3rd floor is in Progress.
   
Tower T1 (4 BHK)  :-  Structure Complete, Water Tank complete, Brick Work Complete, Balcony & Stair case Railing complete. Plaster work complete, Outer Plaster 95% Completed, Internal water supply & Plumbing completed. Terrace waterproofing work Complete 75%. Flooring work in Flats is complete. Corridor Flooring is in Progress. Wall tile work Completed. Internal Painting (Putty & Primer) 1st Coarse Completed. Door Frame work completed & Window Shutter Fixing Start.

Tower  T2 (5 BHK) :-  Structure Complete, Water Tank complete, Brick Work Complete, Balcony & Stair case Railing complete. Plaster work complete, Outer Plaster 95% Completed, Internal water supply & Plumbing completed. Flooring work is in progress. Wall tile work 90% Completed. Internal Painting (Putty & Primer) work is in Progress. Door Frame work completed & Window Shutter Ready to Fix

Tower T13 (2 BHK) :-  Structure Complete, Water Tank complete, Brick Work Complete, Balcony & Stair case Railing complete. Plaster work complete, Outer Plaster Completed, Internal water supply & Plumbing completed. Flooring work in Flats is 35% complete. Corridor Flooring is in Progress.. Wall tile work 95% Completed. Internal Painting (Putty & Primer) 1st Coarse Complete. Door Frame work completed & Window Shutter Fixing Start  

Tower T14 (2 BHK) :-  Structure Complete, Water Tank complete, Brick Work Complete, Balcony Railing complete, Stair case Railing is in progress. Plaster work complete, Outer Plaster 95% Completed, Internal water supply & Plumbing completed. Wall tile work 30% Complete. Internal Painting (Putty & Primer) work 80 % 1st Coarse completed. Door Frame work completed & Window Shutter Ready to Fix

EWS Tower 1  structure complete , Brick work all floor completed Tank Completed, Door window Frame work completed. Internal water supply work completed, Internal sewage work is in progress. Water Tank Completed. Internal Plaster Completed. Outer Plaster 90% Completed,

EWS Tower 2  structure complete , Brick work all floor completed Tank Completed, Door window Frame work completed. Internal water supply work completed, Internal sewage work is in progress.Water Tank Completed. Internal Plaster Completed. Outer Plaster 95% Completed,

The Management is making all-out efforts to complete theproject within the stipulated time.